Who this checklist is for (and who it isn't)
-
The 7-step sourcing checklist
-
Step 1: Lock down the duty point before you call anyone
-
Step 2: Match the datasheet to the process, not to the last project
-
Step 3: Get the API 617 or ISO 10439 compliance statement in writing
-
Step 4: Verify the manufacturer's experience in your envelope
-
Step 5: Run the site utilities check—the one everyone skips
-
Step 6: Sanity-check the lead time and the spares plan against the quote
-
Step 7: Plan the factory acceptance test before you sign
-
Step 1: Lock down the duty point before you call anyone
-
Notes and common errors
The first centrifugal compressor I ever specified was a 1,200 kW unit for a petrochemical client. I was 26, three months into the job, and I approved a datasheet without checking two lines. The unit arrived with the wrong impeller trim for our duty point. We ate about $38,000 in rework and lost five weeks. That was 2017. I've since built the checklist below, and by my rough count it's saved me from at least a dozen repeat performances.
If you're handling centrifugal compressor sourcing—through a distributor, a manufacturer direct, or a sourcing service—this is the seven-step list I run before any quote gets signed. It is not academic. Every step is here because I skipped it once and paid for it.
Who this checklist is for (and who it isn't)
This applies if you're sourcing a centrifugal air compressor or a high pressure centrifugal compressor for a defined process duty: oil and gas, air separation, petrochemical, or any application where gas composition and pressure ratio are non-trivial. I can only speak to industrial B2B orders in the 200 kW–8 MW range. If you're buying a small packaged air compressor off the shelf, this is overkill. Different world, different rules.
The 7-step sourcing checklist
Step 1: Lock down the duty point before you call anyone
Before you request a quote from any centrifugal compressor manufacturer, write down four numbers: inlet flow (actual m³/h), inlet pressure, discharge pressure, and gas composition including molecular weight. If you can't fill in all four, stop. Every quote you get without them is a placeholder, and placeholders are where mistakes move in.
In 2022 I prepared a quote based on a client telling me—by phone—that the duty was "about 40 bar." I built the whole spec around 40 bar. At the kickoff meeting, the process engineer said 68 bar. That's a 70% miss on pressure ratio. We didn't have to redo the compressor, but we did have to redo three months of conversations.
If it isn't written down with units, it isn't the duty point.
Step 2: Match the datasheet to the process, not to the last project
This is the mistake that cost me the $38,000. I assumed "same specifications" across two projects meant identical results from any vendor. Didn't verify. Turned out each OEM interprets "impeller trim" and "surge margin" slightly differently, and the previous project's datasheet was a starting point, not a blueprint.
Every new datasheet needs its own review. Read it line by line against the process data from Step 1. Check the design point, the rated point, and the surge point as three separate numbers. If any of them is missing, that's a red flag.
Step 3: Get the API 617 or ISO 10439 compliance statement in writing
Centrifugal compressors in oil, gas, and petrochemical service are typically specified against API 617 (Axial and Centrifugal Compressors and Expander-compressors) or ISO 10439. For air separation and general industrial air, ISO 8573 also comes into play. These aren't marketing documents—they're the standards that define the acceptance criteria your factory test will be judged against.
Ask for the compliance statement in the quote itself, not after. I've seen three quotes where "API 617 compliant" turned out to mean "designed to similar principles." That's a deal-breaker if your insurer or EPC contractor is checking.
One caveat: standards get revised. I learned the API 617 landscape in 2020. Verify which edition is currently in force before you accept a claim—the version matters as much as the standard itself.
Step 4: Verify the manufacturer's experience in your envelope
A manufacturer that has built 400 centrifugal compressors for air duty may have built four for hydrogen-rich gas at your pressure. That's not a knock on them—but it changes the technical risk profile.
Ask for three reference installations at your pressure ratio, gas molecular weight, and approximate flow. Then actually call one of them. I skipped the call once (busy week). Later I learned the reference unit had been derated twice in two years. Not the manufacturer's fault in that case, but I would have wanted to know before the PO went out.
Step 5: Run the site utilities check—the one everyone skips
This is the step I most consistently see skipped, including by people with more experience than me. The compressor is half the project. The other half is:
- Cooling water availability, quality, and temperature
- Electrical supply capacity and starting current allowance
- Foundation and vibration isolation requirements
- Ambient temperature range at the site (matters more than you'd think)
- Piping and valve sizing on both suction and discharge
If you haven't checked these before the compressor is ordered, they'll find you during commissioning. Trust me on this one.
Step 6: Sanity-check the lead time and the spares plan against the quote
Lead time quotes are the most negotiable number in the pack and also the most likely to slip. The ballpark for a custom high-pressure unit in 2024 was 32–52 weeks from PO, with FAT scheduled around week 28–40. If a manufacturer quotes you 12 weeks for a custom 2 MW unit, ask exactly which configuration is standard stock. The answer is usually none.
While you're at it, price the first two years of spares as a line item. Bearings, seals, and control system spares aren't romantic, but they're where the total cost of ownership (i.e., not just the unit price but everything around it) hides.
Step 7: Plan the factory acceptance test before you sign
Spell out the FAT protocol in the purchase order: which test (ASME PTC 10 is the common reference for compressor performance), which operating points, who witnesses, and what happens if it fails. I've had two FATs where "performance test included" turned out to mean a mechanical run and a vibration reading. Both were technically in scope. Both left me with zero performance data.
Specify the surge margin you'll accept, the vibration limits, and the exact performance points. If the manufacturer pushes back hard on this, that's a red flag—not necessarily a deal-breaker, but flag it and ask why.
Notes and common errors
Assuming the quoted price is the final price. In 2023 I watched a $612,000 quote become a $741,000 invoice, mostly from cooling and piping changes nobody flagged in Step 5. The unit price is an anchor, not the total.
Forgetting that gas composition changes the whole selection. Molecular weight, k-value, and the presence of condensables can shift impeller selection more than the pressure ratio does. If your process gas isn't air, spend an hour with a process engineer before you spend a month with a manufacturer.
Treating "centrifugal" as one category. A single-stage centrifugal air compressor and a multi-stage high pressure centrifugal compressor share a name and almost nothing else operationally. If your sourcing team is comparing them as interchangeable alternatives to screw or reciprocating units, slow down.
Not updating for what's changed since 2020. What was best practice five years ago may not apply in 2025—lead times, efficiency expectations, and digital monitoring options have all moved. The fundamentals (duty point, standards, FAT) haven't changed, but the execution around them has.
I've caught 47 potential errors using this version of the checklist over the last 18 months. Maybe 44—I'd have to pull the log. The point isn't the number. The point is that none of those 47 became a rework invoice.
I can only speak to mid-size industrial orders with reasonably standard gas processes. If you're dealing with cryogenic service, extremely high molecular weight, or sub-sea, the calculus is different and I'd want a specialist in the room. But for the standard industrial sourcing case, these seven steps will keep you out of the kind of trouble I got into in 2017.